Komatsu PW160 flat-rack preparation from Watford to London Gateway

Cargo particulars and task

Our customer needed to move a used Komatsu PW160 wheeled excavator from Watford to London Gateway and prepare it for onward container shipping. The consignment also included a separate excavator bucket and hydraulic hammer.

ENKEL coordinated the UK inland and terminal stages: collection by machine trailer, empty equipment arrangements, loading onto a 40-foot flat-rack, lashing and securing, and the information needed to release the loaded unit for vessel loading.

Komatsu PW160 wheeled excavator and attachments secured on a 40-foot flat-rack at London Gateway
The Komatsu PW160 and its attachments secured on the flat-rack at London Gateway.

Solution

We arranged road transport and coordinated flat-rack preparation at London Gateway. The operational excavator could be driven onto the transport platform, while its loose attachments needed space and separate handling arrangements.

The empty flat-rack had to be released from an off-port depot and brought to the terminal before loading. ENKEL coordinated the equipment release, cargo delivery and terminal booking so that the road and container stages worked together.

Challenges

The shipment required both physical cargo preparation and accurate terminal records. After loading, the terminal team reported 148 cm of overheight and 6 cm of overwidth on each side. These out-of-gauge measurements were passed to the customer for the container record.

The separate bucket and hydraulic hammer needed suitable supports and individual securing. The terminal also required the VGM record to be updated to the terminal-weighing option before it could apply the verified gross mass and clear the associated hold.

What was done

The excavator was collected in Watford on 22 July 2025. ENKEL supplied the driver and delivery details to the terminal in advance and coordinated access to the port’s out-of-gauge cargo area.

On 24 July, the terminal team confirmed that flat-rack loading was complete and supplied photographs of the secured cargo. The photographs show lashing straps, ratchets and timber supports securing the machine and its attachments. ENKEL then coordinated the OOG dimensions and VGM record update with the customer and terminal.

Hydraulic hammer supported on timber and secured with lashing straps on the London Gateway flat-rack
The hydraulic hammer supported on timber and secured separately.
Excavator bucket supported on timber blocks and secured with straps on the flat-rack at London Gateway
Timber supports and lashing straps securing the separate bucket.

Result

On 28 July 2025, the terminal team confirmed that the loaded unit was off hold and ready for the vessel. ENKEL also obtained the terminal’s lashing certificate and forwarded it to the customer on 29 July.

The completed scope brought UK collection, port delivery, flat-rack loading, cargo securing and terminal documentation into one coordinated operation, preparing the excavator and its attachments for the onward sea shipment.